Corby Group Litigation -v- Corby District Council - Technology and Construction Court - Mr Justice Akenhead - [2009] EWHC 2109 (TCC)

Costs sanction - consideration, post Halsey, as to whether or not there had been an unreasonable refusal to mediate

More Cases

Subject
Consideration as to whether a failure to respond to an offer to mediate is, in itself, unreasonable conduct which should lead to cost sanctions. Costs awarded to the successful party on an indemnity basis despite failure to mediate.
Subject
Costs decision. Consideration of validity of Part 36 offer and reasonableness of failure to mediate at an earlier stage.
Subject
Indemnity costs ordered on basis that losing party failed to engage with offer to mediate.